The Updates of the Intimidators #3

Well, here is the third episode of "The Updates of the Intimidators" detailing updates on Intimidator at Carowinds and Intimidator 305 at Kings Dominion.

Intimidator:

On September 28, 2009, the lift hill piece on the ground has gone up thus beginning construction on the 232 ft. lift hill.

On September 29, 2009, the second lift hill support has gone up, a third crane has gone up, and they have begun vertical construction on the station building.

On October 1, 2009, the second set of lift hill track has gone up. The third lift hill support has gone up.

I believe that lift may be topped off in a couple of weeks (probably topped by Halloween)!

Intimidator 305:

On September 26, 2009, the bottom of the first drop and the start of the first turn has gone up and the first lift hill supports have gone up over the week.

Now, in Clint Novak's latest Coaster Crew update for I305 on youtube, he says there will be a ski show in the middle of the ride in 2011. I can't see it in all, but it will further advance Kings Dominion into becoming Cedar Point! WOOT!!!!!!!!!!!