October 2, 2006 - Half of Back to the Future: The Ride in Florida closed, with closure on March 30, 2007.
May 2007 - Construction began with the dismantle of the original Back to the Future concrete, and disposal of the Back to the Future sign.
July 16, 2007 - Simpsons characters were put on the walls and "El Barto" was put on the walls.
October 17, 2007 - Kwik-E-Mart opens.
December 2007 - Simpsons RV is starting to appear.
January 2008 - Outdoor painting begins.
February 2008 - Outdoor painting is finished. Exterior construction begins with the Krusty head.
March 7, 2008 - Circus tents are popping up. Krusty head is ready to go.
March 9, 2008 - Krusty head was put up.
March 15, 2008 - Krustyland sign was put up. Hot dog stand opens. Posters for attractions in Krustyland are coming up.
March 27, 2008 - Simpsons Ride sign and statue of Simpsons were put up. The exterior posters for the rides in Krustyland have gone up.
April 1, 2008 - Googly eyes for the Krusty head have been put up, as well as the banners.
April 10, 2008 - Carnival midway games have been put up.
April 23, 2008 - The Simpsons Ride opens for soft openings.
May 9-11, 2008 - Annual Passholder Previews took place.
July 14, 2008 - The Simpsons Ride in Florida had its 1,000,000th rider.